CBG were appointed following competitive tender to undertake this external refurbishment/ façade remediation contract in Mile End, London. The works at Bresslaw Court involved removing and re-applying an insulated render system for compliance to new regulations.
The existing timber balcony decking was removed and replaced with a new compliant aluminium system. Whilst undertaking the works it was discovered that the secondary framing system was insufficient so we were instructed to install additional metal framing to ensure the building could support the new insulated render system.