CBG Construction Ltd were appointed as Design and Build contractor for the external refurbishment of South Cliff Tower, Eastbourne, which is an existing 18 storey residential tower block adjacent to the seafront in this busy East Sussex resort.

The project involved waterproofing works to the balconies on the tower, concrete repairs, a new EWI rendering system, new windows, new balcony doors and an external redecoration package. The works were undertaken in one continuous phase from the West elevation, using mast climbers.

Following completion of the extensive concrete repair programme we applied a new waterproof layer to all of the balcony decks followed by a total door replacement programme with new high quality aluminium units. This included the creation of a new 150mm up-stand to all thresholds to prevent water ingress. Upon completion the South elevation was completely redecorated in anti-carbonation paint.